The time t required to do a job varies inversely as the number of people working. It takes 4 hr for 7 cooks to prepare the food for a wedding rehearsal dinner. How long will it take 8 cooks to prepare the dinner?

in progress 0
Dulcie 4 years 2021-08-27T06:47:26+00:00 1 Answers 19 views 0

Answers ( )

    0
    2021-08-27T06:49:03+00:00

    9514 1404 393

    Answer:

      3 1/2 hours

    Step-by-step explanation:

    If there are 8/7 times as many cooks, it will take 7/8 the amount of time. (That’s what “inversely proportional” means.)

      (7/8)(4 h) = 28/8 h = 3 1/2 h

    It will take 8 cooks 3 1/2 hours to prepare the dinner.