Question
The time t required to do a job varies inversely as the number of people working. It takes 4 hr for 7 cooks to prepare the food for a wedding rehearsal dinner. How long will it take 8 cooks to prepare the dinner?
in progress
0
Mathematics
4 years
2021-08-27T06:47:26+00:00
2021-08-27T06:47:26+00:00 1 Answers
19 views
0
Answers ( )
9514 1404 393
Answer:
3 1/2 hours
Step-by-step explanation:
If there are 8/7 times as many cooks, it will take 7/8 the amount of time. (That’s what “inversely proportional” means.)
(7/8)(4 h) = 28/8 h = 3 1/2 h
It will take 8 cooks 3 1/2 hours to prepare the dinner.