A crane lifts a 425 kg steel beam vertically a distance of 64 m. How much work does the crane do on the beam if the beam accelerates upward
Question
Lost your password? Please enter your email address. You will receive a link and will create a new password via email.
Answers ( )
Answer:
work done= 48.96 kJ
Explanation:
Given data
mass of load m= 425 kg
height/distance h=64 m
acceleration a= 1.8 m/s^2
The work done can be calculated using the expression
work done= force* distance
but force= mass *acceleration
hence work done= 425*1.8*64= 48,960 J
work done= 48.96 kJ