Share
Pete works in road construction as a greader operator. His regular work week is 40 hours. During the busy season, he often has to work overt
Question
Pete works in road construction as a greader operator. His regular work week is 40 hours. During the busy season, he often has to work overtime. For overtime hours worked Monday to Friday, he earns Time and a half. If he has to work on Saturday, he earns double time and a half. How much will Pete make if he works 45.25 hours during the week and 5.75 hours on Saturday? His regular salary is $15.77/h
in progress
0
Mathematics
3 years
2021-08-02T00:46:07+00:00
2021-08-02T00:46:07+00:00 1 Answers
73 views
0
Answers ( )
Step-by-step explanation:
15.77 x 40 + 15.77(1.5)(5.25) + 15.77(2)(5.75) =
630.8+124.19+181.36
$936.35