there is one agent that sells tickets to the movie theater. customers arrive at the ticket outlet at the rate of 10 per hour. if on average a customer waits in line for 6 minutes, what is the expected number of customesr in the queue (aka as average
-
Answer:there should be 1 customer waiting in line at the ticket outlet.Step-by-step explanation:To calculate the expected number of customers in the queue, we can use the following formula:Expected number of customers = Arrival rate * Average waiting timeIn this case, the arrival rate is 10 customers per hour and the average waiting time is 6 minutes. Converting the waiting time to hours, we get:Expected number of customers = 10 customers/hour * (6 minutes / 60 minutes/hour) = 1 customerSo the expected number of customers in the queue is 1. This means that on average, there should be 1 customer waiting in line at the ticket outlet.