    Answer:

    m=36kg

    h=1.5m

    f=36×10

    =360N

    w=f×d

    =360×1.5

    =540N/M²

    Explanation:

    mass is 36 kg

    height is 1.5m

    to find force applied we need to multiply mass and gravity which is 10

    we get force as 360N

    to get workdone we need to multiply force and distance in our case it is height

    then we get workdone as 540N/M²

    0
    2021-07-17T01:07:48+00:00

    540N/m²

    Explanation:

    m=36kg

    h=1.5

    g=10m/s²

    W=36×1.5×10

    =540N/m²